Current roadworks and closures

Some planned works have been delayed or cancelled while flood recovery efforts are underway.

Stay up to date with what's happening on our roads, follow us on Facebook

Information on this page is intended as a guide. Start and end dates are estimates only and may change for various reasons including weather  conditions.

Last updated - Tuesday, 4 June 2024

Yass

Current Road closures: 

There are no current road closures reported

Patching Truck / Cold Mix:
Local roads - Ongoing

Grading work:

Yass River Road (Gundaroo End) - In Progress

Dog Trap Road - In Progress

 Wargeila Road - In Progress

Fairy Hole Road - Completed 

Black Range Road - Programmed

Gums Lane - In Progress 

Drainage Work

Laverstock Road - In Progress

Grant Funded works

LRCI - Gums Lane Resheeting Seg 2 & 3; in progress

RERRF - Yass Valley Way - Heavy Patching; to be undertaken in 2024-25

RRRP - Yass Valley Way Roundabout repairs (Service Centre end); assessment of work and scope preparation

Deferred due to cost

Murrumbateman

Current Road Closures

There are no current road closures reported

Patching Truck/ Cold mix 

Grading Work

Dog Trap Road - In Progress  

Gums Lane - In Progress

Drainage Work:

Boutchers Lane & Drive - Scheduled

Grant Funded works  

Binalong, Bookham and Bowning

Current Road Closures
There are no current road closures reported

Patching Truck/Cold Mix 

Grading Work  

Drainage Work 

Grant Funded Works  

Gundaroo and Sutton

Current Road closures: 
There are no current road closures reported

Patching Truck / Cold Mix:

Gundaroo Road/Sutton - In Progress

Marked Tree Road - Programmed

Grading Work 

Yass River Road - Gundaroo End - In Progress 

Gravel Resheeting  

Drainage Work 

Grant Funded works

RRRP - Gundaroo Road Guardrail replacement - In Progress 

Spring Range and Wallaroo

Current Road Closures
There are no current road closures reported

Patching Truck/Coldmix

Grading Work

Shephards Road - Scheduled

Drainage Work

Grant funded works

LRCI - Tallagandra Lane Resheeting Seg 8, 9 &10; programmed for May  

Wee Jasper and The Mullion

Current Road Closures
There are no current road closures reported

Patching Truck/Cold Mix

Wee Jasper Road - In progress

Grading Works

Wee Jasper Road - Scheduled

Gravel Resheeting 

Drainage Work

Longley's Road - Scheduled

Grant Funded Works

RERRF- Wee Jasper Road - Heavy Patching programmed for May